Typical lead times

Typical ranges from order to delivery, as a guide for planning. They are not a promise - every job is different and your quotation confirms the programme.

WorkTypical lead timeNotes
Steel beams for an extension or loft3-7 working days from approved drawingsPrimed. Longer for galvanised or fire-protected steel
Goalpost frames and small frames1-2 weeksDepends on drawings and site measure
Staircases and balustrades2-4 weeksIncluding drawings and approval; finishes add about a week
Balconies (sets)3-6 weeksGalvanised and powder coated (duplex) finishes add 1-2 weeks
Gates, railings and architectural metalwork2-4 weeksBespoke designs may need approval drawings first
Mezzanine floors2-4 weeksPlus decking and building control coordination
Commercial steel framesAgreed per projectProgramme set out in the tender return
CNC plasma cut plates (PSS CUT)Often within daysDepends on material stock and quantity

How to get your steel sooner

  • Send the engineer's calculations and drawings with your enquiry
  • Reply to drawing approvals quickly - it is often the longest wait
  • Agree the finish early, as galvanising and powder coating are booked with specialist finishers
  • Give us clear access and delivery details

Plan your own dates with the programme planner.

Questions

Frequently asked questions

Often within 3-7 working days of approved drawings for primed domestic beams. Ask us for urgent work.

Waiting for drawing approval, missing design information, special finishes and unusual sections or grades.