Typical lead times
Typical ranges from order to delivery, as a guide for planning. They are not a promise - every job is different and your quotation confirms the programme.
| Work | Typical lead time | Notes |
|---|---|---|
| Steel beams for an extension or loft | 3-7 working days from approved drawings | Primed. Longer for galvanised or fire-protected steel |
| Goalpost frames and small frames | 1-2 weeks | Depends on drawings and site measure |
| Staircases and balustrades | 2-4 weeks | Including drawings and approval; finishes add about a week |
| Balconies (sets) | 3-6 weeks | Galvanised and powder coated (duplex) finishes add 1-2 weeks |
| Gates, railings and architectural metalwork | 2-4 weeks | Bespoke designs may need approval drawings first |
| Mezzanine floors | 2-4 weeks | Plus decking and building control coordination |
| Commercial steel frames | Agreed per project | Programme set out in the tender return |
| CNC plasma cut plates (PSS CUT) | Often within days | Depends on material stock and quantity |
How to get your steel sooner
- Send the engineer's calculations and drawings with your enquiry
- Reply to drawing approvals quickly - it is often the longest wait
- Agree the finish early, as galvanising and powder coating are booked with specialist finishers
- Give us clear access and delivery details
Plan your own dates with the programme planner.
Questions
Frequently asked questions
Often within 3-7 working days of approved drawings for primed domestic beams. Ask us for urgent work.
Waiting for drawing approval, missing design information, special finishes and unusual sections or grades.